Concrete for a strip footing — cubic yards and 80 lb bags from the footing's length, width and depth.
Price is an editable estimate — change it to your supplier's price. Cost = total quantity (with waste) × your price. Estimate only, not a quote.
Cubic feet = length (ft) × width (in ÷ 12) × depth (in ÷ 12) · Cubic yards = cu ft ÷ 27 · Bags (80 lb) = cu ft ÷ 0.60
A 50 ft footing, 20 in wide × 10 in deep: 50 × 1.67 × 0.83 = 69.44 cu ft = 2.57 cubic yards = 116 × 80 lb bags. With 10% waste: 2.83 cubic yards = 128 bags.
The load it carries, the soil's bearing capacity and your local building code — not this calculator. This tool only figures the concrete volume for a footing size you enter; footing sizes are set by load and soil, and most footings must also sit below the local frost line.
Most do — two continuous horizontal bars are a common minimum in residential strip footings, with vertical dowels where a stem wall ties in. The exact steel is a code and engineering call; the rebar calculator can figure lengths once the layout is set.
A 50 ft footing like the example is about 2.6 cubic yards — well past bag territory for most people (116 bags). Ready-mix on a truck is usually the practical choice beyond about a yard; bags suit short footing runs and post footings.